Case Study 2
Combined Heating and Cooling in a Paint shop
- Customer-A leading two-wheeler automobile manufacturer
- Application– Surface Cleaning in Paint Shop
- Hot water requirement– 4pre-treatment tanks, each tank to be maintained at 60-70 Deg C
- Source of heat replaced – Liquified Petroleum Gas (LPG)
- Boiler consuming around 650 kg of LPG per day
- Combined Heating and Cooling
- Condenser side – replaced the fired boiler Evaporator side- replaced the chiller which was used for electrode position process.